What the developer needs before it can hand over
Under the statutory contract for a strata property, a developer may only let you into possession once five things are true. They are not optional and they are not sequenced to suit the sales calendar.
- A certificate of completion and compliance has been issued.
- The separate strata title for your parcel has been issued by the appropriate authority.
- Water and electricity are ready for connection to your parcel.
- You have paid everything due under the agreement, including the instalment that falls at handover.
- Any alteration or additional work you asked for has been completed.
Handover must be supported by the certificate of completion and compliance, and it includes the handing over of the keys. A set of keys with no certificate behind it is not vacant possession.
What a CCC actually certifies
The certificate of completion and compliance — everyone calls it the CCC — is issued under the Street, Drainage and Building Act 1974 and the by-laws made under it. It certifies that the accommodation has been completed and is safe and fit for occupation. It is signed off by the project's own qualified person, the architect or engineer, who carries the professional liability for saying so.
The 30-day rule nobody mentions at handover
This is the part worth reading twice. Thirty days after the developer serves notice asking you to take possession, you are deemed to have taken vacant possession — whether or not you ever went, collected the keys, or set foot in the building.
Everything that runs from vacant possession runs from that deemed date. The twenty-four month defect liability period. The eight and twenty-four month releases of the money held by the developer's solicitor. Maintenance charges. A buyer living overseas who leaves the notice unopened for two months has not paused anything; they have spent two months of their defect period.
When the strata title is not ready
Strata titles are issued by the land office, and they are often slower than the building. The contract anticipates it: where the title has not been issued for a reason that is not the developer's fault, the developer may apply to the Controller of Housing for written certification allowing it to deliver vacant possession anyway, within the same delivery deadline.
If that is what has happened, the handover must come with a copy of that written certification from the Controller. Ask for it. Once the title is eventually issued, the developer must execute and deliver a registrable transfer to you at no further cost — and that is the event that triggers the 2.5% instalment for the transfer and title.
If handover is late
The developer has thirty-six months from the date of the agreement to deliver vacant possession on a strata property. Past that, it owes liquidated damages calculated from day to day at 10% a year of the purchase price, running until the day possession is actually delivered. You do not need to prove a loss, and if it is not paid you may deduct it from an instalment still owing.
What to do in the first thirty days
- Inspect before you accept the keys, and take photographs with dates on them.
- Ask to see the CCC, and check it is the full certificate rather than a partial one.
- If the strata title is not yet issued, ask for the Controller's written certification.
- Write up every defect and send it in writing — email is fine — rather than raising it on site.
- Copy your defect notice to the developer's solicitor, not only the developer.
- Take meter readings on the day, and find out when maintenance charges start.