Progressive Payment on a New Launch: What You Pay, and When

You pay 10% on signing the sale and purchase agreement, then the rest in instalments as each stage of construction is certified complete — your bank releases the money, not you. The last 5% is held by the developer's solicitor and paid out over the two years after you get the keys.

Buying something that has not been built yet feels like it should be complicated, and the money side of it is the part people most expect to be. It is not. The schedule is fixed by law, it is printed in the agreement you sign, and the developer cannot change a single percentage in it. This guide walks through what leaves your account and what leaves the bank's, in the order it happens.

Last updated 28 November 2026 · 7 min read

The schedule is law, not the developer's choice

A new condominium or serviced apartment in Malaysia is sold on a statutory contract. For a building to be subdivided into parcels — which is what strata property is — that contract is Schedule H to the Housing Development (Control and Licensing) Regulations 1989. The developer fills in the names, the parcel and the ringgit amounts. The stages, the percentages and the order they fall in are set by the regulations, and are the same whichever developer you buy from.

That is worth knowing before you sit down at the sales gallery, because it means the payment schedule is not something to negotiate or be talked through quickly. It is the same document every buyer in the country signs, and you can read it before you go.

What you pay at each stage

Ten per cent on signing, then eight construction stages, then the balance around handover. Each instalment falls due within thirty days of the developer giving you written notice that the stage is complete, certified by the project's architect.

WhenStage% of price
On signingImmediately upon signing the agreement10%
During constructionWork below ground level, including the foundation10%
The structural framework of your parcel15%
Walls of your parcel, with door and window frames in position10%
Roofing and ceiling, electrical wiring, plumbing without fittings, gas piping and internal telecoms cabling10%
Internal and external finishes, including wall finishes10%
Sewerage works serving the building5%
Drains serving the building2.5%
Roads serving the building2.5%
At handoverVacant possession, with water and electricity ready for connection17.5%
Transfer instrument and strata title delivered to you or your solicitor2.5%
After handoverHeld by the developer's solicitor as stakeholder for defects5%
Schedule H, Third Schedule. The twelve rows total 100% exactly.

Most of this is the bank's money, not yours

The common misreading of that table is that you have to find the money twelve times. You do not. If you are buying with a loan, the 10% on signing is yours — along with the booking fee it is usually drawn from, your legal fees and your stamp duty. Almost everything after that is released by your bank directly to the developer as each stage is certified.

  • You pay the 10% on signing, plus legal fees and stamp duty on the transfer and the loan.
  • Your bank releases each construction instalment on the architect's certificate — you sign nothing further at each stage.
  • You start paying interest only on what the bank has actually released, so the monthly figure climbs as the building goes up.
  • Your full monthly instalment begins once the loan is fully drawn down, at or around handover.

That rising interest during construction is the part worth planning for. For the first year or two it is small, and by the final stages it is close to a full instalment — while you may still be paying rent somewhere else.

What happens at handover

Vacant possession is the moment the property becomes yours to use. Under Schedule H it carries 17.5% of the price, and it is only due when water and electricity are ready for connection — not when the building merely looks finished.

A further 2.5% falls due when the developer delivers the instrument of transfer together with the original issue document of strata title. On many projects the title takes longer than the keys, so this instalment often sits outstanding for a while after you have moved in.

The 5% that is kept back for defects

The final 5% is paid at handover but not to the developer. It goes to the developer's solicitor, who holds it as stakeholder and releases it in two halves: 2.5% eight months after you take vacant possession, and 2.5% twenty-four months after.

That money is the leverage behind the defect liability period. Any defect that appears within twenty-four months of vacant possession, and is down to poor workmanship, poor materials or the building not matching the approved plans, must be repaired by the developer at its own cost within thirty days of your written notice.

If the developer is late — and if you are

Schedule H gives the developer thirty-six months from the date of the agreement to deliver vacant possession. Miss it, and the developer owes you liquidated damages calculated from day to day at 10% per annum of the purchase price, running from the end of that period until the day you actually take possession. You do not have to sue for it or prove a loss; if it is not paid, you are entitled to deduct it from an instalment still due.

The obligation runs the other way too. An instalment unpaid after its thirty-day window attracts late payment charges at the same 10% per annum, calculated from day to day. Where the delay is the bank's — a loan from a government body being slow to release — the developer is not entitled to charge you for it.

PeriodRate
Developer must deliver vacant possession36 months from the agreement—
Liquidated damages if lateFrom the end of month 36 until handover10% a year on the purchase price
Your instalment falls due30 days from written notice—
Late payment charges if you are lateFrom the day it falls due10% a year on the unpaid amount
Defect liability24 months from vacant possession—
Schedule H clauses 25, 10 and 30. The two 10% rates are symmetrical by design.

Working out what you need up front?

Tell me the project and the unit, and I will put the numbers together on your figures — the cash on signing, the legal fees and stamp duty, and what the monthly instalment looks like as the loan draws down.

Common questions

How much cash do I need on day one for a new launch?
The 10% due on signing, less whatever booking fee you have already paid, plus your legal fees and stamp duty on the transfer and on the loan agreement. The rest of the purchase price is released by your bank in stages as the building goes up.
Can a developer change the payment percentages?
No. The stages and the percentages are set by Schedule H to the Housing Development (Control and Licensing) Regulations 1989. The developer fills in the ringgit amounts that the percentages work out to, and nothing else in that table is theirs to set.
When do my monthly loan instalments start?
Interest starts as soon as the bank makes its first release, and it rises with each stage because you are charged on what has actually been drawn. The full monthly instalment begins once the loan is fully drawn down, which is at or around vacant possession.
What is the 5% held back at handover for?
Defects. It is paid at vacant possession to the developer's solicitor, who holds it as stakeholder and releases 2.5% eight months after you take possession and 2.5% twenty-four months after — the same period over which the developer must put right any defect you report in writing.
What happens if the project is handed over late?
Schedule H allows thirty-six months from the date of the agreement. Beyond that the developer owes liquidated damages at 10% a year of the purchase price, calculated daily until you take vacant possession, and you may deduct it from a later instalment if it is not paid.
Is the schedule the same for a landed house?
No. Landed property on its own title is sold under Schedule G, which has a different stage list and a different delivery period. This guide is Schedule H, which covers condominiums and serviced apartments.