The Defect Liability Period: Your 24 Months, and the 5% Behind It

Twenty-four months from the day you take vacant possession. Any defect down to poor workmanship, poor materials or the building not matching the approved plans must be repaired by the developer at its own cost within 30 days of your written notice — and if it is not, you can do the work and take the cost out of the 5% the developer's solicitor is holding.

Almost everyone who buys a new home knows there is a defect period. Far fewer know that the contract does not simply ask the developer nicely: it sets a deadline, names the remedy if the deadline is missed, and keeps 5% of the price in a solicitor's hands for exactly that purpose. This guide is about using it.

Last updated 28 November 2026 · 5 min read

What is covered, and for how long

The period is twenty-four months from the date you take vacant possession — and note that the contract treats possession as taken thirty days after the developer's notice, whether or not you collected the keys. It covers your own parcel, the building, and the common property, so a cracked lobby floor or a leaking car park is as much within it as a door in your own hallway.

What qualifies is any defect, shrinkage or other fault that becomes apparent in those twenty-four months and is down to one of three things: defective workmanship, defective materials, or the building not having been constructed in accordance with the approved plans and the descriptions in the agreement. Fair wear from your own use is not in it; a hairline crack that opens up as the structure settles usually is.

The 30-day clock starts from writing

Once the developer receives written notice from you, it has thirty days to repair and make good, at its own cost. The words that matter there are written and received. A conversation with the site office starts nothing.

  • Put every defect in writing, with photographs and the date you found it.
  • Email is fine. Keep the sent copy and any acknowledgement.
  • List each defect separately rather than as one general complaint.
  • Copy the developer's solicitor on the same notice — the reason is below.

If they do not fix it: the self-help route

This is the part of the contract most buyers never use, usually because nobody tells them it is there. If the developer has not made good within those thirty days, you may have the work done yourself and recover the cost from the money its own solicitor is holding. There is a sequence, and it has to be followed in order.

  1. Give written notice of the defect, and wait out the 30 days.
  2. After the 30 days, notify the developer of what the repair will cost — before any work starts.
  3. Give the developer a further 30 days from that notice to do the work itself.
  4. If it still does not, carry out the works as soon as practicable afterwards.
  5. Send the developer's solicitor a written demand specifying the cost.
  6. The solicitor must release that cost to you from the stakeholder sum within 30 days of receiving the demand.

The 5%, and how to stop it leaving

At handover, 5% of the purchase price is paid not to the developer but to the developer's solicitor, who holds it as stakeholder. It is released in two halves on a fixed timetable.

PortionReleasedMeasured from
2.5%At the expiry of 8 monthsThe date you take vacant possession
2.5%At the expiry of 24 monthsThe date you take vacant possession
Schedule H, Third Schedule, item 5.

That timetable runs regardless of whether you have complained — unless you have served a copy of your defect notice on the developer's solicitor before the release date. Do that, and the solicitor may not release that half to the developer until it has received a certificate signed by the developer's architect confirming the defect has been repaired and made good.

A practical timetable

  • Week 1 after handover: full inspection, written snag list to the developer and its solicitor.
  • Month 7: re-inspect and re-notify anything outstanding, before the first 2.5% is due to be released.
  • Months 8 to 23: report new defects as they appear — the period covers anything that becomes apparent, not only what you saw on day one.
  • Month 23: final inspection and written notice of anything still unrepaired, before the second 2.5% falls due.

Found something after handover?

Send me the photographs and I will help you word the notice and get it to the right people — the developer and its solicitor both.

Common questions

How long is the defect liability period in Malaysia?
Twenty-four months from the date you take vacant possession of a strata property, which the contract treats as thirty days after the developer's handover notice whether or not you collected the keys.
What counts as a defect?
Any defect, shrinkage or other fault that appears within the period and is caused by defective workmanship, defective materials, or the property not having been built in accordance with the approved plans and the descriptions in your agreement. It covers the common property as well as your own unit.
How long does the developer have to repair it?
Thirty days from receiving your written notice, at its own cost and expense.
What if the developer does not repair it?
You may do the work and recover the cost from the 5% held by the developer's solicitor — but only if you first notify the developer of the cost, give it a further thirty days to do the work itself, and then make written demand on the solicitor, who must pay within thirty days.
Can I stop the 5% being released while a defect is unresolved?
Yes. Serve a copy of your written defect notice on the developer's solicitor before the relevant release date. That half then cannot be released until the solicitor receives a certificate from the developer's architect confirming the repair has been made good.